Schedule for Phase 2 (January-February 2004)
(updated after ISI meeting)
Planning Committee (Ed, Teruko, David)
Week of Dec 20:
- F1E1 done
Week of Jan 12:
- F1E4 partly done by all annotators at all sites
Week of Jan 19:
- F1E1 and F1E4 done by everybody
- meeting at ISI
- J1E1 IL0 trees fixed by CMU
Week of Jan 26:
- J1E1 done by Researchers, using new method
- Phone call and new instructions finalized
- J1E1 done by Annotators, using new method
- S1E1, S1E2 IL0 trees fixed by NMSU
- Discussion and training, both locally and inter-site
Week of Feb 4:
- S1E1, S1E2 done by all annotators at all sites
- A1E1, A1E2 IL0 trees fixed by UMD, and files posted
- K1E1, K1E2 IL0 trees fixed by ISI, sentences interleaved, and files
posted
- Discussion and training, both locally and inter-site
- Evaluation measures refined
Week of Feb 9:
- Columbia, MITRE, CMU: Version A (A1E1, A1E2, [sentence-interleaved K1E1, K1E2])
- UMD, NMSU, ISI: Version B (A1E2, A1E1, [sentence-interleaved K1E2, K1E1])
- J2E1, J2E2 IL0 trees fixed by CMU, and files posted
- H2E1, H2E2 IL0 trees fixed by Columbia, sentences interleaved, and
files posted
Week of Feb 16:
- Columbia, MITRE, CMU: Version A (J2E1, J2E2, [sentence-interleaved S2E1, S2E2])
- UMD, NMSU, ISI: Version B (J2E2, J2E1, [sentence-interleaved H2E2, H2E1])
- H1E1, H1E2 IL0 trees fixed by Columbia, and files posted
- F2E1, F2E2 IL0 trees fixed by MITRE, sentences interleaved, and files posted
Week of Feb 23:
- Columbia, MITRE, CMU: Version A (H2E12, [sentence-interleaved F2E1, F2E2])
- UMD, NMSU, ISI: Version B (H2E21, [sentence-interleaved F2E2, F2E1])
Week of Mar 1:
- final scores evaluated over all 144 annotated texts, and report
prepared
- report sent to Boyan and others
For 6 sites x 2 annotators per site x 12 E texts = 144 annotation
activities